Construction Updates
Destination Zoo

Getting to the Zoo is easy using our updated driving directions.

The ramp to southbound 45 is closed permanently. The ramp to Highway 45 southbound at Watertown Plank Road is now open. All on and off ramps at Highway 100 and I-94 are open.

November 3-6, 2016

Thursday (11/3)

  • Zoo Interchange Project
    • a lane will be closed during the day Watertown Plank Rd WB from Swan Blvd to Discovery Pkwy for sign structure work.

Friday (11/4)

  • Zoo Interchange Project
    • a lane will be closed during the day Watertown Plank Rd WB from Swan Blvd to Discovery Pkwy for sign structure work.

Saturday (11/5)

  • Zoo Interchange Project
    • only long-term closures in effect.

Sunday (11/6)

  • Zoo Interchange Project
    • only long-term closures in effect.

Long-Term Closures

  • Zoo Interchange Project
    • a lane will be closed HWY 100 entrance ramp to I-94 WB through TBD for metering issues.
    • a lane will be closed I-41/894 NB from National Ave to Greenfield Ave through 11/1 for roadway construction.
    • there will be a full closure Greenfield Ave entrance ramp to I-41/894 NB through 11/1 for roadway construction.
    • there will be a full closure National Ave entrance ramp to I-41/894 NB through 11/1 for roadway construction.
    • there will be a full closure HWY 100 entrance ramp to I-43 (to I-41/894 NB) through 11/1 for roadway construction.
    • a lane will be closed North Ave entrance ramp to I-41 NB through 11/7 for deep storm sewer work.
    • a lane will be closed Curtis Rd NB/SB at I-94 through early November 2016 for roadway construction.
    • a lane will be closed I-94 EB from Sunnyslope Rd to HWY 100 through late November 2016 for roadway construction.
    • there will be a full closure Fairview Ave WB from 116th St to Curtis Rd through early December 2016 for retaining wall construction (local access maintained).
    • there will be a full closure Fairview Ave EB from 118th St to 116th St through early December 2016 for retaining wall construction (becomes one-way WB only).
    • there will be a full closure Bluemound Rd entrance ramp to I-41 NB through late December 2016 for ramp reconstruction.
    • there will be a full closure of the Zoo Int W-N system ramp through late May 2017 for ramp reconstruction.
    • there will be a full closure of the Zoo Int N-E system ramp through late May 2017 for ramp reconstruction.
    • there will be a full closure Wisconsin Ave EB/WB from 95th St to 97th St through late May 2017 for reconstruction.
    • there will be no access from the Watertown Plank Rd EB entrance ramp to I-41 SB to the Zoo Int N-E system ramp through June 2017 for roadway reconstruction.
    • there will be a full closure Bluemound Rd entrance ramp to I-41 SB through late August 2017 for ramp reconstruction.
    • there will be a full closure Lincoln Ave entrance ramp to I-41/894 NB through early Fall 2017 for roadway construction.
    • there will be a full closure I-94 WB exit ramp to HWY 100 NB through late November 2017 for roadway reconstruction.
    • there will be a full closure I-94 WB exit ramp to HWY 100 SB (from I-94 WB and I-41/894 NB) through late November 2017 for roadway reconstruction.
    • there will be a full closure of the Zoo Int E-S system ramp through late November 2017 for ramp reconstruction.
    • there will be a full closure Greenfield Ave entrance ramp to I-41/894 NB (to I-41 NB and I-94 WB) 11/1 through late 2017 for ramp reconstruction.
    • there will be a full closure Oak Leaf Trail NB/SB at I-94 through late 2017 for bridge demolition.
    • there will be a full closure I-41/894 SB exit ramp to Greenfield Ave (from I-94 WB and I-41 SB) through late 2017/early 2018 for roadway reconstruction.
    • there will be a full closure I-41 NB exit ramp to Bluemound Rd through late April 2018 for ramp reconstruction.
    • there will be a full closure Schlinger Ave EB/WB under I-41/894 through early Summer 2018 for project construction.
    • Hank Aaron State Trail will be closed to pedestrians from 94th Pl to Oak Leaf Trail through early Summer 2018 for project construction.
  • Dousman Rd/Golden Lake Rd/I-94 Project
    • there will be a full closure Dousman Rd NB/SB from Valley Rd to Delafield Rd through early November 2016 for roadway work.
    • there will be a full closure Golden Lake Rd NB/SB from Valley Rd to Delafield Rd through late November/early December 2016 for roadway work.
  • I-94/CTH F and Nemahbin Project
    • a left-turn lane will be closed CTH F entrance ramp to I-94 EB through 10/28 for roadway construction.
    • a left-turn lane will be closed CTH F entrance ramp to I-94 WB through 10/28 for roadway construction.
    • a left-turn lane will be closed I-94 EB exit ramp to CTH F through 10/28 for roadway construction.
    • a left-turn lane will be closed I-94 WB exit ramp to CTH F through 10/28 for roadway construction.
    • lanes will be closed CTH F NB/SB over I-94 through 10/28 for roadway construction.
  • Westin Hotel Utility Work
    • a lane will be closed I-794 EB exit ramp to Jackson St/Van Buren St for utility work (there will be overnight double lane closures on the ramp through 10/31 for this work as well).

* Note that these closures are weather dependent and subject to change.

For more information on Zoo Interchange closures, visit the Wisconsin Department of Transportation website.